A Block-By-Block Look At NW 23rd Street This Fall

Warm autumn light on a quiet brick storefront block, with a clean sidewalk, empty cafe seating and a tree with golden-brown leaves.

This fall, the one-lane stretch of NW 23rd Street has been at the Broadway end, the end farthest from Mesta Park. In August, the city's progress report marked new sidewalks and driveways finished on the western blocks, the stretch of 23rd closest to Mesta Park and Heritage Hills. That same report listed the next sections in order, moving east toward Broadway.

The project is Oklahoma City's $9.3 million NW 23rd Street streetscape, which runs from Western Avenue to Broadway. Construction began on January 12, 2026. The city's announcement lists median removal, wider ADA sidewalks, new lighting, added bus stops, a traffic signal at Hudson, resurfacing and waterline replacement. The money comes from ACOG and the 2017 bond program. The city's monthly updates describe the schedule as "approximately 18 months for overall completion." Counting from that January start, the whole street would be finished around the middle of 2027. The city has not published an exact end date.

Because the western blocks are the furthest along, the part of 23rd closest to the historic neighborhoods has the most finished concrete. Walking the street west to east shows how far along each section is.

Western To Walker, Where The Work Started

The city's August 2026 project update reported that sidewalk and driveway work between Lee and Dewey was finished and that sanitary sewer work from Western to Lee was done. Between Walker and Dewey, demolition, conduit, and the footings for light poles and pedestrian poles were complete. Curbs, gutters, ramps and sidewalks were being poured there at the time. The next four weeks of work on that stretch were limited to driveway placement.

Two of this year's restaurant changes are on the west end. Kaizume opened in early May at 1501 NW 23rd, in the space that used to be Syrup. The Oklahoman reported that it is chef Richard Ly's high-end sushi and seafood restaurant. Chef Chris McKenna worked with Ly on the menu. Kaizume opened in the middle of the street rebuild, so its first guests walked past construction to get there.

A few blocks east, Chick-N-Beer moved a short distance down the street. It closed at 715 NW 23rd in January 2026 and reopened in October as CNB at 733 NW 23rd, inside Bungalow 23. CNB's own site lists the new location as open daily. The space opened up when Chino's Mexicano closed in late August, according to The Oklahoman's fall roundup of openings and closings. For anyone who walks over from Mesta Park, CNB is now a few doors from where it was before, and the sidewalk in front of it is new.

Walker To Robinson, The Middle Blocks Through The Summer

East of Walker, the August update listed the next work in order. First came sidewalks and parking between Walker and Hudson. Next, Hudson closed for inlet installation while crews poured new footings, sidewalks and driveways between Hudson and Harvey. After that, Harvey Avenue closed completely for concrete demolition and replacement between Harvey and Robinson. The bulletin said southbound access on Robinson would be restored near the end of that phase.

The businesses on these blocks stayed open through the summer construction, and the schedule was adjusted around some of them. News 9 reported that Big Truck Tacos closed from June 29 to July 5 so a week of work could get done all at once, and reopened afterward. The same report described district businesses sharing information so customers could keep supporting the shops along the street. KOCO reported that work on Boomtown Creamery's block was moved from June and July to the fall, after the ice cream shop's busiest season.

Robinson To Broadway, The East End This Fall

The August look-ahead ended at the east end. It said a full eastbound closure was starting between Robinson and Broadway, with demolition and subgrade work to prepare for paving. By fall, the lane restriction was on that stretch. News 9's October 12 traffic roundup reported NW 23rd narrowed to one lane in each direction between Broadway and Robinson. ODOT's November 12 traffic advisory still listed the one-lane restriction between Broadway and Robinson.

For someone driving east from Mesta Park or Heritage Hills to dinner or a holiday errand near Broadway, that leaves the slowdown at the far end of the trip, from Robinson on.

The Gold Dome At Classen

The Gold Dome at NW 23rd and Classen is the best-known building on the street. It opened in 1958 as Citizens State Bank and was the fifth geodesic dome built anywhere in the world. Route 66 News reported in October that the building had been sold at a sheriff's auction, that a court hearing on the sale is set for late December, and that the city council approved $3 million in tax-increment financing for the Gold Dome on the day it went to auction. The new sidewalks around the dome are going in while the building's next use is still being decided.

What The Finished Blocks Look Like Next Year

When the streetscape is complete, the changes already visible on the western blocks will run all the way to Broadway. The city lists wider sidewalks, better lighting, shade, waterline replacement and fresh pavement. The center median will be gone, bus stops will be added, and a new signal will go in at Hudson. The monthly updates are posted on the city's NW 23rd streetscape project page.

Until the full street is finished, the western end is the easiest part of 23rd to use. Kaizume and CNB sit on blocks where the city has reported finished sidewalk and driveway work. The Hudson-to-Robinson blocks had their closures over the summer, and the one-lane stretch this fall has been at the Broadway end.

If you live near 23rd and are wondering how a rebuilt commercial street could shape your own plans over the next year, Laura Loves Houses follows Mesta Park and Heritage Hills one block at a time, including the block at the end of yours. Schedule a consultation and we'll walk through it together.

Work With Us